Background
Followmont Transport finished building new depots at Woree in Cairns and Paget in Mackay, Queensland, in late 2019. As part of its commitment to operating in an environmentally conscious way, both depot designs focused on minimising their carbon footprint, which led Followmont to Green Frog Systems solar lighting.
Considerations and Challenges
- The depots operate 24 hours a day, seven days a week.
- Awning mounted floodlights only reach part of each yard.
- Trucks need to be loaded and unloaded in different areas as yard use changes.
Solution
GFS-200 solar street lights were supplied on concrete bases with forklift tine slots, so each light can be picked up and moved with a forklift. This lets the depots light loading areas outside the reach of the fixed floodlights, so trucks can be loaded and unloaded anywhere in the yard.
Thanks to the hinge plate design, Followmont’s in house team installed the lights within hours.
Products Used
- 5 × GFS-200 solar street lights at Paget, Mackay
- 2 × GFS-200 solar street lights at Woree, Cairns
- Concrete bases with forklift tine slots
Results
- Loading areas beyond the floodlights are lit at night.
- Lights can be moved by forklift as yard layouts change.
- Installation was completed in hours by the depot’s own team.
Testimonial
“Simon from Green Frog Systems was a standout from all other providers that were contacted when seeking quotes. Throughout the process, we were kept up to date on the status of our lights and all items were delivered with urgency. The consistent level of service provided by Simon has made Green Frog Systems our go-to for any solar lights and we look forward to working with them in the future.”
Brooke Tice, Project and Property Coordinator, Followmont Transport
Conclusion
Relocatable solar lights on forklift movable bases gave Followmont flexible lighting across its Cairns and Mackay yards, with no cabling and no impact on the depots’ energy use. Read more about our temporary and relocatable solar lighting.